Douglas Avenue narrows to one lane Oct. 20 as parking garage construction reaches the street
The developer of the 309-space Douglas Parking Center says single-lane flagging on Douglas Avenue runs Oct. 20 through Nov. 5, with the project's only full closure Nov. 9β10 for crane removal. Traffic control plans are still pending City of Dunedin approval, and an earlier city notice listed different dates.

Editorial graphic by Dunedin Community Website. Illustrative blurred community background: Wesley Chapel, Florida (August 2024), LittleT889 / Wikimedia Commons (CC0). Photo source Β· License
Douglas Avenue is still fully open, but the developer building downtown Dunedin's new parking garage has posted Tuesday, Oct. 20 as the start of the first lane restriction. From that date through Thursday, Nov. 5 β about 13 working days, Monday through Friday only β one lane at 968 Douglas Avenue closes and traffic alternates in both directions through a single 11-foot lane under certified flaggers, according to the project's construction page. The reason is the final bay of the structure: it sits along the Douglas Avenue frontage, so the crane needs the near lane.
Posted Douglas Avenue traffic phases
- Oct. 20 β Nov. 5
One lane closed; traffic alternates through an 11-foot lane under flaggers, weekdays only
- Nov. 9 β 10
Full closure just south of Skinner Blvd. for crane removal; detour via Skinner, Broadway, Main
- Nov. 11
Both lanes reopened by Wednesday morning
Source: douglasparkingcenter.com
What drivers and walkers should expect
The page lists a 15 mph work-zone speed limit, work hours of 7 a.m. to 5 p.m. and all precast deliveries finished by 3 p.m., with no weekend work. The sidewalk on the project side closes during that stretch, with signed crossings sending pedestrians to the east sidewalk, while the Pinellas Trail along the site's western edge stays open behind protective fencing.
The developer also says no construction activity or delivery traffic is scheduled during the Oct. 10β11 Art & Craft festival weekend, and that access to adjacent homes and businesses is maintained during both traffic phases.
The two-day full closure, and the detour
The only full closure of the project is scheduled for Monday and Tuesday, Nov. 9β10, when the erection crane comes down. Douglas Avenue would be blocked just south of Skinner Boulevard, with Virginia, Monroe and Grant streets staying open for local access and through traffic signed onto Skinner Boulevard, Broadway and Main Street in both directions. Both lanes are to reopen by Wednesday morning, Nov. 11.
Dates could still move
Two caveats are worth noting before planning around these dates. The traffic control plans were drafted by Spartan Safety Services and are still pending City of Dunedin approval, and the developer says the schedule page β current as of Sept. 18 β is updated weekly, with the city notified before any closure begins if weather or logistics shift a date. An Aug. 13 city newsletter had described a different sequence: a lane closure Oct. 12 to 23 and a full road closure Oct. 26 to 27, also pending city approval. The city added the private project to its Engage Dunedin page because the impacts reach beyond the site.
What's being built
The Douglas Parking Center is a four-story, 309-space public parking garage, a total-precast structure manufactured by Metromont and erected by Hawkins Construction. Overall completion is targeted for the first quarter of 2027.
Continue this story for free.
Stay informed about Dunedin. Enter your email to access the full story and receive local news and community updates.
Free to read Β· No password to remember
New here? Weβll email you a sign-in link and code. Already a reader? Use your usual email.
Read next

Dunedin's second property tax town hall is Tuesday at the Hale Center
The City of Dunedin's second Property Tax Town Hall begins at 6 p.m. Tuesday, Oct. 6, at the Hale Senior Activity Center, with a panel on property taxes and the city's projected $4.7 million to $7.6 million revenue hit if Amendment 3 passes.
Read the story β